Below please find a copy of the notice every business on Main Street from Gilbert to North Grand Avenue should be getting. In a nutshell, they are ready to begin Stage 2, which will be from Gilbert Street to Ferguson. That is scheduled to run from now to May 24th.

  • Stage 3 – Main Street from Clark to Ferguson, May 28-June 14
  • Stage 4 – Main Street from Ferguson to Lane, June 17-July 12
  • Stage 5 – Main Street from Lane to North Grand Ave., May 16-July 5

Asphalt paving of Main Street is tentatively scheduled right now for July or August. That is expected to take approximately 2 weeks to complete. Until then, the road will remain open to traffic.

Curb and gutter work, as well as removing the brick strip from the sidewalk, will be done on a stage-by-stage basis, Traffic will be maintained on Main Street while that work is going on. However, on-street parking will be restricted in areas as the work progresses.

Please see the complete notice for more information, or contact City Engineer Brian Sullivan at City Hall. You may also contact me if you need help in obtaining information, but Brian is the primary contact person. The Chamber and Main Street Charles City Office will try to keep you updated and informed, and is in the process of assigning volunteer Block Captains to help act as your personal liaison.